STOREBAELT and COLT Survey and Burial, Korsor Denmark
|
Hydrographic and Diving Services
|
Global Crossing Denmark and Colt Technology Services. Marine Hydrographic and diving services to undertake cable damage survey of the Storebaelt and Colt Shore Ends off Korsor, Denmark and subsequent burial of the crossing.
|
November
|
|
Helsingborg, Sweden Cable Re-location
|
Marine Consultancy
|
Global Crossing Sverige AB. Project Engineering and Operational Supervision on behalf of the customer to plan and execute the re-location of shore end cables (3) for out-fall dredging and construction.
|
November
|
|
ACE System Liberia
|
Diving Supervisor
|
Alcatel-Lucent. Project Engineer/Dive Supervisor acting as Customer Representative to advise on and monitor direct shore end installation and protection works in Monrovia.
|
November to December
|
|
ACE System Gambia and Gabon Shore End Installations
|
Project Engineering and Consultancy
|
Alcatel-Lucent. Providing technical and operational support and acting as Customer Representatives on site to advise on and monitor pre laid shore end installation works in Banjul and Libreville.
|
July to December
|
|
BIOS Israel
|
Project Eng’r/Dive Supervisor
|
Alcatel-Lucent. Project Engineer/Dive Supervisor acting as Customer Representative to advise on and monitor directional drilling new ducts, shore end installation works and burial.
|
June to December
|
|
Articulated Pipe
|
55mm
|
Supply of 55mm Articulated to Alcatel-Lucent for Shore End Protection Projects World Wide.
|
July
|
|
CANALINK Canary Isles
|
Project Eng’r/Beach Master
|
Alcatel-Lucent. Project Engineer/Beach Master acting as Customer Representative to advise on and monitor shore end installation works.
|
April to June
|
|
CANALINK Spain
|
Project Eng’r/Beach Master
|
Alcatel-Lucent. Project Engineer/Beach Master acting as Customer Representative to advise on and monitor shore end installation works in Rota (Cadiz).
|
March
|
|
ALBA-1 Cuba
|
Diving Project Engineer
|
Alcatel-Lucent. Diving Project Engineer acting as Customer Representative for Shore End Installation and Cable Protection Works.
|
February
|
|
ECFS St. Martin
|
Cable Survey & Protection
|
Orange-FT. Near shore diving works to survey shore ends, remove debris and install articulated pipe protection.
|
January
|
|
WACS Congo
|
Marine Project Engineer
|
Alcatel-Lucent. Marine Project Engineer to Supervise Shore End Installation and Cable Protection Works.
|
January to February
|